Northern Sewer Network Upgrades Project Update 14 October 2026
16 October 2026
Progress to Date
We have:
- Constructed 8 inspection chambers.
- Works Areas 6 and 7 have been completed ahead of schedule.
Good progress continues to be made, and we currently expect Phase 1b to be completed in May 2027, approximately one month earlier than the previously reported forecast completion date of late June 2027.
Installed approximately 557 metres of foul sewer pipe.