Residents invited to sewer upgrade update as project passes 1,900 metres of new pipework

More than 1.9 kilometres of new sewer pipework and 28 new inspection chambers have now been installed as part of the Northern Sewer Network Upgrades, with both phases of the project remaining on schedule despite periods of poor weather.

Residents and businesses affected by the works are invited to attend a public meeting on Monday 30 November, where the Minister for Infrastructure and project officers will provide an update on progress, answer questions and hear feedback from the community.

The Minister for Infrastructure and officers will be on hand to provide an update on the latest steps in the project, answer questions and hear feedback and concerns from residents and businesses.

Meeting details

  • Date: Monday 30 November 2026
  • Time: 6–7pm
  • Location: United Reform Church Hall, Sion

According to the latest project update, Phase 1a remains on track for completion in April 2027, while Phase 1b is expected to be completed in May 2027.

To date, construction teams have installed 1,300 metres of foul sewer pipe and 18 inspection chambers in Phase 1a, together with a further 661 metres of foul sewer pipe and 10 inspection chambers in Phase 1b.

Read this week’s latest project update newsletter below, and find further information by heading to gov.je/NorthernSewerUpgrades.

Newsletters to keep you in the know.

Subscribe to the free Parish newsletter below to receive news, events, community updates and opportunities to get involved in St Helier straight to your inbox.

Sign me up for emails related to: