Works being carried out by the Parish

Road nameVallee des Vaux
Nature of repairsCreation of Virtual Footpath/ traffic calming
Type of traffic disruptionStop/ Go traffic management
Estimated completion time1 month
Start date30 March 2024
Supporting documentsProposed improvements
Works Completed?
Road nameHalkett Street/ Hilgrove Street
Nature of repairsResurfacing/ public realm improvements to pedestrian precinct
Type of traffic disruptionMajor highway works
(please note all businesses in the area remain open)
Estimated completion timeMay
Start date22 January 2024
Supporting documentsDesign Proposal
Works Completed?

Works recently completed by the Parish ✅

Road nameRue des Cotils
Nature of repairsSeveral patches of road require resurfacing
Type of traffic disruptionRoad closure
Estimated completion time4 days
Start dateMonday 10 June 2024
Supporting documentsDiversion route
Works Completed?Works complete 12 June.
Road nameLa Freedee Lane
Nature of repairsSeveral patches of the road require resurfacing
Type of traffic disruptionRoad closure
Estimated completion timeEstimated completion on Friday 31 May
Start dateTuesday 28 May
Supporting documentsDiversion route
Works Completed?Works completed Thursday 30 May.
Road nameCollege Hill
Nature of repairsEmergency maintenance works to carriageway
Type of traffic disruptionRoad closure (access to premises maintained)
Estimated completion time1 day
Start date30 May
Supporting documents
Works Completed?Work completed Friday 31 May.
Road nameFern Valley
Nature of repairsSurface water improvements
Type of traffic disruptionRoad closure (access to premises maintained)
Estimated completion time1 month
Start date5 April
Supporting documentsLetter to residents
Works Completed?Works completed 28 May.

Other works within the Parish and wider Island

To find out about road closures, diversions and traffic works including resurfacing of roads across Jersey please follow the link to the TrafficWorx map and search using road names or postcodes for details.