Road WorksTravaux des C’mîns

The Parish of St Helier must continue to make essential repairs and improvements to roads across the Parish. Should you have any problems with any of the works that are currently underway please get in touch with our Infrastructure Department on 01534 811844 or [email protected].

We apologise for any inconvenience Parish works may cause and request your patience and cooperation.

Works being carried out by the Parish

Road nameColombus Street
Nature of repairsEssential repairs to the existing road humps and surface water gullies
Type of traffic disruptionRoad closure
Estimated completion timeOne week
Start dateMonday 17 February
Supporting documents
Works Completed?
Road namePomona Road Neighbourhood Improvement Area
Nature of repairsFor full details of the scheme please click here
Type of traffic disruptionRoad closure/ reversed flow
Estimated completion time25 April
Start date3 February
Supporting documentsDiversion
Works Completed?
Road nameHilgrove Street
Nature of repairsExtension of granite paved footpaths and cobbled roadway
Type of traffic disruptionRoad closure
Estimated completion time6 weeks
Start date10 February
Supporting documentsExtent of works
Works Completed?

Works recently completed by the Parish ✅

There are no works that have been completed within the last month.

Other works within the Parish and wider Island

To find out about road closures, diversions and traffic works including resurfacing of roads across Jersey please follow the link to the TrafficWorx map and search using road names or postcodes for details.